Demolition and Dismantling UK - Brown and Mason
 

Demolition and dismantlingCommercial and City Centre Demolition
Watney House, London SW1

This project comprised the demolition down to, but not including, the suspended ground floor slab of an existing 10 storey office building.

In addition to the demolition of the building itself, the contract included the removal of major items of mechanical and electrical plant at basement and other levels. The contract also included the removal and disposal of various forms of asbestos materials.

The methodology deployed on this contract took due cognisance of the fact that the London Underground Victoria Line passed at a depth of some 14 metres below ground level at the North west corner of the building.

Asbestos Waste Containers & Disposal UK
Asbestos Waste Containers & Disposal UK

Demolition facts

Most of the brick waste sent to landfill or recycled emanates from the demolition sector. Brick waste in construction is generally sent to landfill.

CONTACT: B&M@brownandmason.ltd.uk